A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

A.
Support the team in identifying the area of development and address the gap.
Answers
A.
Support the team in identifying the area of development and address the gap.
B.
Dissolve the team and include the team members in other existing teams.
Answers
B.
Dissolve the team and include the team members in other existing teams.
C.
Identify the struggling team members and move them out of the team.
Answers
C.
Identify the struggling team members and move them out of the team.
D.
Set up a clear expectation that the team is to deliver as in their previous projects.
Answers
D.
Set up a clear expectation that the team is to deliver as in their previous projects.
Suggested answer: A