A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems.
What should the project manager do next?
A.
Apply the terms and conditions of the contract with penalties.
B.
Issue a change request to reflect the anticipated date for training.
C.
Help the customer find an alternative location to start the training.
D.
Update the project schedule with the new date for training.