A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

A.
Discuss this issue with the affected team members and support them during the transition.
Answers
A.
Discuss this issue with the affected team members and support them during the transition.
B.
Start looking for replacements as soon as possible to help prevent any schedule slippage.
Answers
B.
Start looking for replacements as soon as possible to help prevent any schedule slippage.
C.
Engage with the project sponsor to ensure that this change does not affect the project execution.
Answers
C.
Engage with the project sponsor to ensure that this change does not affect the project execution.
D.
Determine the impact to the project and implement mitigations per the project management plan.
Answers
D.
Determine the impact to the project and implement mitigations per the project management plan.
Suggested answer: D