Question 256 - PMP discussion
A company plans to initiate a project involving a new technology. Approval for the project is required.
What should the project manager do?
A.
Review the cost and schedule baselines for execution.
B.
Define change management for the new technology.
C.
Identify the risks in implementing the new technology.
D.
Analyze the cost and identify the project benefits.
Your answer: