A key project stakeholder does not attend any of the project meetings and is providing false information that the project team is not delivering on time.

What should the project manager do to address this situation?

A.
Email the latest status report to the key stakeholder.
Answers
A.
Email the latest status report to the key stakeholder.
B.
Discuss communication needs with the key stakeholder.
Answers
B.
Discuss communication needs with the key stakeholder.
C.
Create a new communication artifact for the key stakeholder.
Answers
C.
Create a new communication artifact for the key stakeholder.
D.
Share the meeting recordings with the key stakeholder.
Answers
D.
Share the meeting recordings with the key stakeholder.
Suggested answer: B