An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer.

What guidance should the product manager provide to improve the requirement development?

A.
Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.
Answers
A.
Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.
B.
Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.
Answers
B.
Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.
C.
Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.
Answers
C.
Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.
D.
Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.
Answers
D.
Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.
Suggested answer: C