Question 284 - PMP discussion
An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).
What should the project lead do?
A.
Discuss the product owner's recommendations with the team and implement the agreed-on solutions
B.
Allow the team to self-organize so one of the resources can lead the team to achieve consensus
C.
Discuss the recommendations with the test manager and request better quality control
D.
Facilitate the meeting so anyone can share their ideas and is heard during the session
Your answer: