A project manager has been assigned to an education project with the objective of training a workforce in application development. One of the deliverables is to provide internships to the best students in the customer's active projects.

However, the customer does not have enough projects in progress right now. The project manager decides to create several internal projects in order to ensure the internships.

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three.)

A.
Create a work breakdown structure (WBS) of the new scope with the internal projects.
Answers
A.
Create a work breakdown structure (WBS) of the new scope with the internal projects.
B.
Create a change request with the scope of the new internal projects.
Answers
B.
Create a change request with the scope of the new internal projects.
C.
Use the project's contingency budget.
Answers
C.
Use the project's contingency budget.
D.
Influence the client to initiate a new project.
Answers
D.
Influence the client to initiate a new project.
E.
Manage the quality of the delivery.
Answers
E.
Manage the quality of the delivery.
Suggested answer: A, D, E