Question 300 - PMP discussion
During a project's third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
A.
Guide the team to revert back to the forming and storming stages.
B.
Discuss the decrease in productivity with human resources (HR).
C.
Convene a team building event to address key performance indicators (KPIs).
D.
Escalate the issue to the project sponsor.