Question 316 - PMP discussion

Report
Export

A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.
Release the resources and plan for a project completion celebration.
Answers
A.
Release the resources and plan for a project completion celebration.
B.
Ensure that knowledge transfer activities are executed as planned.
Answers
B.
Ensure that knowledge transfer activities are executed as planned.
C.
Hold a steering committee meeting to inform them of the project completion.
Answers
C.
Hold a steering committee meeting to inform them of the project completion.
D.
Mark the product backlog completion status and update the communications management plan.
Answers
D.
Mark the product backlog completion status and update the communications management plan.
Suggested answer: B