ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 318 - PMP discussion

Report
Export

Due to delays on some activities, one of the project team members has increased the scope without any approval.

What should the project manager do next?

A.
Remove the changes to match the original requirements.
Answers
A.
Remove the changes to match the original requirements.
B.
Add team members to the project to avoid more schedule delays.
Answers
B.
Add team members to the project to avoid more schedule delays.
C.
Update project documentation with the new scope.
Answers
C.
Update project documentation with the new scope.
D.
Evaluate the impacts of the changes that were made to the project.
Answers
D.
Evaluate the impacts of the changes that were made to the project.
Suggested answer: D
asked 23/09/2024
Arlind Tereziu
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first