Question 320 - PMP discussion
During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?
A.
Update the risk register and project log, and manage the budget closely.
B.
Revise the project scope accordingly to cope with the budget changes.
C.
Submit a change request to accelerate the project as requested.
D.
Ask upper management for more funds, and update the project budget.