Question 346 - PMP discussion

Report
Export

The product owner decides to launch a product after a couple of releases, knowing that the minimum viable product (MVP) lacks some features. One of the key stakeholders, the marketing vice president, is not happy with the results and questioned the release decision.

What should the project manager do?

A.
Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future
Answers
A.
Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future
B.
Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing
Answers
B.
Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing
C.
Assume the responsibility for product releases, making the final call on when something is ready for customer launch
Answers
C.
Assume the responsibility for product releases, making the final call on when something is ready for customer launch
D.
Escalate the issue to the sponsor, questioning the authority of the key stakeholder regarding the product launch decision
Answers
D.
Escalate the issue to the sponsor, questioning the authority of the key stakeholder regarding the product launch decision
Suggested answer: A