In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing.

The software update will be accomplished using an agile approach in order to minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches.

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?

A.
Weekly colocated meetings with the relevant stakeholders
Answers
A.
Weekly colocated meetings with the relevant stakeholders
B.
Biweekly conference calls with the relevant stakeholders
Answers
B.
Biweekly conference calls with the relevant stakeholders
C.
Weekly one-on-one meetings with each of the relevant stakeholders
Answers
C.
Weekly one-on-one meetings with each of the relevant stakeholders
D.
Biweekly written status reports from the relevant stakeholders
Answers
D.
Biweekly written status reports from the relevant stakeholders
Suggested answer: A