A vendor informed the project manager that a critical resource will be on a long leave of absence.

The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.

What should the project manager do next?

A.
Request a replacement resource
Answers
A.
Request a replacement resource
B.
Perform a cost-benefit analysis
Answers
B.
Perform a cost-benefit analysis
C.
Implement risk responses
Answers
C.
Implement risk responses
D.
Perform Integrated Change Control
Answers
D.
Perform Integrated Change Control
Suggested answer: D