Question 363 - PMP discussion
A vendor informed the project manager that a critical resource will be on a long leave of absence.
The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
A.
Request a replacement resource
B.
Perform a cost-benefit analysis
C.
Implement risk responses
D.
Perform Integrated Change Control