Question 378 - PMP discussion
During the design phase, a project manager realizes that the project will benefit from using adaptive tools. The effectiveness of this approach has been proven in past projects inside the organization.
What should the project manager do first?
A.
Update project documents to include adaptive tools and artifacts and plan the first iterative session
B.
Contact the project sponsor and request new team members who are familiar with adaptive projects
C.
Confirm team capabilities before introducing adaptive tools and artifacts to the project
D.
Freeze the design stage and look for an external resource to run iterative design at extra cost
Your answer: