An agile project is running its fifth iteration out of eight. After the last iteration planning the team was informed that there is a new competitor in the market, and it is necessary to move faster to ensure market share is not missed.
What should the project manager do?
A.
Add the competitor's functionalities to the product backlog to improve the product
B.
Ask the sponsor to add more people to the team
C.
Help the team to find a new approach to launch the product as soon as possible
D.
Ask the team to increase the velocity to launch the product as soon as possible