ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 397 - PMP discussion

Report
Export

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.

How should the project manager handle this situation?

A.
Implement crashing to compress the schedule and improve the schedule performance index (SRI).
Answers
A.
Implement crashing to compress the schedule and improve the schedule performance index (SRI).
B.
Implement fast-tracking to compress the schedule and improve the SPI
Answers
B.
Implement fast-tracking to compress the schedule and improve the SPI
C.
Perform conflict management using the project's resource management plan.
Answers
C.
Perform conflict management using the project's resource management plan.
D.
Review the risk management plan to evaluate the probability and impact of these delays
Answers
D.
Review the risk management plan to evaluate the probability and impact of these delays
Suggested answer: D
asked 23/09/2024
zulmaidi mr
38 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first