Which two actions should a project manager consider while launching a new virtual team?

(Choose two.)

A.
Recruit the best resources within the organization to be part of the virtual team
Answers
A.
Recruit the best resources within the organization to be part of the virtual team
B.
Evaluate the project manager's own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls
Answers
B.
Evaluate the project manager's own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls
C.
Identify the types and quantities of resources required for each work package or activity
Answers
C.
Identify the types and quantities of resources required for each work package or activity
D.
Establish in the beginning, how progress will be monitored and the best means for communicating progress
Answers
D.
Establish in the beginning, how progress will be monitored and the best means for communicating progress
E.
Verify if team members are on more than one team and cannot devote enough time to this team
Answers
E.
Verify if team members are on more than one team and cannot devote enough time to this team
Suggested answer: C, D

Explanation:

One of the comments below mentions that C is too obvious and is required for both virtual and non-virtual teams. Exactly, when you know it is a required step then why skip it? Before you even move on the option E, you first need to identify the what kind of resources or skills are required for the project. Once you have identified the type and amount of resources needed only then you can start looking at the resources available and consulting the resource schedule to identify which resources are available through out the project.

Explanation: