During the retrospective ceremony, the agile team is talking about the product owner's expectations not being met.

What should the project manager have done at the beginning of the project?

A.
Defined the expected agile team contribution in the creation of the backlog
Answers
A.
Defined the expected agile team contribution in the creation of the backlog
B.
Assessed the capabilities of the agile team and planned for the required training
Answers
B.
Assessed the capabilities of the agile team and planned for the required training
C.
Defined the team ground rules and shared project vision
Answers
C.
Defined the team ground rules and shared project vision
D.
Communicated project vision and sprint goals clearly to the team
Answers
D.
Communicated project vision and sprint goals clearly to the team
Suggested answer: D