ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 428 - PMP discussion

Report
Export

A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.

What should the project manager do?

A.
Hold a stakeholder meeting to align timelines and scope expectations
Answers
A.
Hold a stakeholder meeting to align timelines and scope expectations
B.
Crash the schedule to shorten the timeline while keeping the scope unchanged
Answers
B.
Crash the schedule to shorten the timeline while keeping the scope unchanged
C.
Update the cost management plan to allocate more resources to the project to finish the scope earlier
Answers
C.
Update the cost management plan to allocate more resources to the project to finish the scope earlier
D.
Reduce the scope of the project by removing activities and shortening the timeline
Answers
D.
Reduce the scope of the project by removing activities and shortening the timeline
Suggested answer: A
asked 23/09/2024
Welber Santos de Oliveira
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first