The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline. There have been complaints from some stakeholders about some of the team members' performance. The project manager wants to understand the situation and provide feedback to the team as soon as possible.

What three actions should the project manager take to address this situation? (Choose three.)

A.
Define team ground rules
Answers
A.
Define team ground rules
B.
Perform a retrospective session
Answers
B.
Perform a retrospective session
C.
Implement daily team meetings
Answers
C.
Implement daily team meetings
D.
Request a manager performance review
Answers
D.
Request a manager performance review
E.
Conduct an annual review
Answers
E.
Conduct an annual review
Suggested answer: A, B, C