After a meeting with the customer, the project manager receives special recognition because the project is always on schedule. Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

A.
Share the customer feedback with the project team
Answers
A.
Share the customer feedback with the project team
B.
Follow the meeting agenda and make a list of the next deliverables
Answers
B.
Follow the meeting agenda and make a list of the next deliverables
C.
Document this feedback in the meeting minutes
Answers
C.
Document this feedback in the meeting minutes
D.
Start planning how to improve the dates of next deliverables
Answers
D.
Start planning how to improve the dates of next deliverables
Suggested answer: A