Question 830 - PMP discussion
After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW). These changes would improve the project outcome.
What should the project manager do next?
A.
Consult the list of selected vendors for the bid and evaluate a possible change of vendor.
B.
Revise the procurement control process to avoid undesired changes that might affect the schedule.
C.
Assess the situation as an opportunity for improvement and perform a risk analysis.
D.
Conduct an audit on the procurement process and inform the vendor about the audit's observations.
Your answer: