Question 836 - PMP discussion
A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business.
What should the project manager do to ensure business value is delivered early?
A.
Create robust incentives to the team members to encourage speedy delivery
B.
Create a detailed project plan and escalate delays to the functional managers
C.
Break down the deliverables into sprints and deliver value incrementally
D.
Fast track the project and monitor tasks closely to ensure timely delivery
Your answer: