ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 840 - PMP discussion

Report
Export

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

A.
Create a risk register to track the risks and request additional budget.
Answers
A.
Create a risk register to track the risks and request additional budget.
B.
Analyze the impact against the release plan if the blocker is not addressed.
Answers
B.
Analyze the impact against the release plan if the blocker is not addressed.
C.
Work with the project owner to prioritize the product backlog.
Answers
C.
Work with the project owner to prioritize the product backlog.
D.
Escalate the situation to the project sponsor for a possible resolution.
Answers
D.
Escalate the situation to the project sponsor for a possible resolution.
Suggested answer: B
asked 23/09/2024
Pawel Lenart
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first