A project manager is executing a large project with many stakeholders. One of the primary stakeholders is requesting a change to the project scope. The project manager knows that this scope change will not require much effort from the project team. The project manager is worried that going through the full change control process will hold up the project schedule.

What should the project manager do?

A.
Ask the primary stakeholder for their official approval to avoid the change control process.
Answers
A.
Ask the primary stakeholder for their official approval to avoid the change control process.
B.
Implement the change in order to avoid changes to the schedule baseline.
Answers
B.
Implement the change in order to avoid changes to the schedule baseline.
C.
Reject the change request because the project is already being executed.
Answers
C.
Reject the change request because the project is already being executed.
D.
Submit a formal change request since the change is affecting the project baseline.
Answers
D.
Submit a formal change request since the change is affecting the project baseline.
Suggested answer: D