A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

A.
A detailed mitigation plan on the risks for each work method and the tools used
Answers
A.
A detailed mitigation plan on the risks for each work method and the tools used
B.
A technology roadmap for creating similar deliverables in the future with the same tools
Answers
B.
A technology roadmap for creating similar deliverables in the future with the same tools
C.
An agreed-upon work method and tools that should fit the business need and project constraints
Answers
C.
An agreed-upon work method and tools that should fit the business need and project constraints
D.
A consensus that everything will run as anticipated once the tools and work methods are identified
Answers
D.
A consensus that everything will run as anticipated once the tools and work methods are identified
Suggested answer: C