Question 887 - PMP discussion
An agile team has started a new project. When should the project manager organize their first team retrospective?
A.
When more than a few weeks have passed.
B.
When the team reaches a major milestone.
C.
When the team completes a release of a monumental increment.
D.
When the work is progressing well through the team.