During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to know about the deliverable.

What should the project manager do next?

A.
Check if these stakeholders attend regular project meetings.
Answers
A.
Check if these stakeholders attend regular project meetings.
B.
Meet with these stakeholders to review the project charter.
Answers
B.
Meet with these stakeholders to review the project charter.
C.
Review the project charter to validate this claim
Answers
C.
Review the project charter to validate this claim
D.
Validate if the project charter changed from the original one.
Answers
D.
Validate if the project charter changed from the original one.
Suggested answer: B