List of questions
Related questions
Question 1121 - PMP discussion
A project manager has recently been asked to take over an existing project that is halfway through execution. The project sponsor asked the project manager to ensure that the work carried out and the product being created do not deviate from the prescribed business value.
What should the project manager do to achieve this goal?
A.
Review the requirements management plan.
B.
Monitor the work breakdown structure (WBS).
C.
Carry out quality audits and failure analyses.
D.
Review the benefits realization plan.
Your answer:
0 comments
Sorted by
Leave a comment first