An organization is going through a transformation, migrating most of its projects from a predictive to an agile approach. The marketing VP, who is also a key stakeholder, expressed a concern about losing control of the features that will be implemented in the product lines.

What should the project manager responsible for this project do?

A.
Email the marketing VP with a cost-benefit analysis of the new model, detailing how the company will improve its products.
Answers
A.
Email the marketing VP with a cost-benefit analysis of the new model, detailing how the company will improve its products.
B.
Schedule a meeting with the marketing VP to discuss and clarify the benefits of using an agile approach.
Answers
B.
Schedule a meeting with the marketing VP to discuss and clarify the benefits of using an agile approach.
C.
Apply influence with other key stakeholders to mitigate risks that may be generated by the marketing VP.
Answers
C.
Apply influence with other key stakeholders to mitigate risks that may be generated by the marketing VP.
D.
Review the issue with the marketing VP and request additional project funding for team training.
Answers
D.
Review the issue with the marketing VP and request additional project funding for team training.
Suggested answer: B