Due to price inflation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced.
What is the first approach the project manager should take?
A.
Ask the business stakeholders to reduce the number of features required for the product.
B.
Delay the hiring of the additional resource until market conditions are favorable to work within project requirements.
C.
Ask the functional managers to source a less experienced and less expensive team member for the project.
D.
Request the current team to analyze the work planned for the additional resource.