Question 1132 - PMP discussion
Two project managers are working on separate projects that have identified the same subject matter expert (SME) as critical to their projects. Project A is using a predictive approach and Project B is using an agile approach.
Which project should the SME be allocated to?
A.
The project with the less experienced project manager to improve the likelihood of success.
B.
The project with the highest score in the program to improve the likelihood of success.
C.
Project A, because project planning was based on the assumption that the SME would be available.
D.
Project B, because success in an agile project is determined by technical excellence.
Your answer: