List of questions
Related questions
Question 1134 - PMP discussion
During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.
What should the project manager ask the team to do next?
A.
Negotiate the estimation so it gets smaller.
B.
Break down the larger activities into smaller ones.
C.
Resize the story points.
D.
Execute the smaller estimated activities.
Your answer:
0 comments
Sorted by
Leave a comment first