Question 1142 - PMP discussion
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. In a project review meeting. a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
A.
Assign a technical writer to the project.
B.
Develop a standard for document quality control.
C.
Ask the project management office (PMO) to support and review all deliverables.
D.
Log the issue in the risk register and the issue log.
Your answer: