A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.

What should the project manager do first?

A.
Continue the project while trying to obtain the permit.
Answers
A.
Continue the project while trying to obtain the permit.
B.
Update the risk management plan.
Answers
B.
Update the risk management plan.
C.
Review lessons learned from previous projects.
Answers
C.
Review lessons learned from previous projects.
D.
Obtain the permits before continuing the build.
Answers
D.
Obtain the permits before continuing the build.
Suggested answer: D