A project team has been formed, and the tasks have been assigned to each team member. All team members have agreed to follow a hybrid project approach.

What should the project manager do to ensure the team performs as an organized unit?

A.
Call a team meeting to discuss team members' strengths and weaknesses.
Answers
A.
Call a team meeting to discuss team members' strengths and weaknesses.
B.
Advise the team to adjust their work habits and behaviors to allow for better conflict resolution.
Answers
B.
Advise the team to adjust their work habits and behaviors to allow for better conflict resolution.
C.
Establish rules and regulations for team members with consequences if the goals are not reached.
Answers
C.
Establish rules and regulations for team members with consequences if the goals are not reached.
D.
Establish team behavior and develop an understanding of how to work together.
Answers
D.
Establish team behavior and develop an understanding of how to work together.
Suggested answer: C