ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1176 - PMP discussion

Report
Export

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

What should the project manager do next?

A.
Deliver what was planned in the project management document according to the specifications
Answers
A.
Deliver what was planned in the project management document according to the specifications
B.
Update the assumptions log and change log, and implement the change control process
Answers
B.
Update the assumptions log and change log, and implement the change control process
C.
Inform the client that the project cannot meet the project timeline and additional costs will be incurred
Answers
C.
Inform the client that the project cannot meet the project timeline and additional costs will be incurred
D.
Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests
Answers
D.
Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests
Suggested answer: B
asked 23/09/2024
Reza Mirabrishami
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first