A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Explanation:
An RFP (request for proposal) is a document that solicits proposals from potential vendors for a specific project or service. An RFP typically describes the project scope, requirements, evaluation criteria, and instructions for submitting proposals. An RFP is the best document for the company to use to obtain and compare information on cabling services and costs from various vendors, as it allows the company to evaluate the vendors' qualifications, experience, approach, and pricing12.
Question 162
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
Explanation:
According to 6 Techniques for Running Project Management Meetings, one of the best practices for effective project meetings is to assign meeting roles to stay focused. By delegating the roles and responsibilities of facilitator, timekeeper, scribe, and presenter, the project manager can ensure that the meeting agenda is followed, the action items are recorded, and the outcomes are communicated. This can also increase the engagement and accountability of the project team members, and reduce the frustration of the project manager.
Question 163
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
Explanation:
An issue log is a tool that records and tracks any issues that arise during the project. It helps the project manager to identify, prioritize, assign, monitor, and resolve the issues in a timely manner. An issue log can also include information such as the issue description, impact, status, owner, and resolution date1. An issue log is different from a defect log, which records and tracks the defects or errors in the project deliverables. A risk register is a tool that records and tracks the potential risks that may affect the project objectives. A change log is a tool that records and tracks the changes that are made to the project scope, schedule, budget, or quality2.
Question 164
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
Explanation:
The project manager should inform the project sponsor about the issue and seek their guidance and support. The project sponsor is the person who provides the resources and authority for the project, and who can help resolve any conflicts or problems that may arise. The project manager should not withdraw the offer, ignore the lawsuit, or use a third-party company without consulting the project sponsor first, as these actions may have legal, ethical, or financial implications for the project and the organization12.
Question 165
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
Explanation:
The waterfall methodology is a project management framework that follows a linear and sequential process, where each stage of the project must be completed before moving on to the next one. The stages of the waterfall model are initiation, planning, execution, and closure, as described in the question12.
Question 166
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?
Explanation:
Informal communication is a type of communication that is casual, spontaneous, and unstructured. It does not follow any predefined rules, protocols, or formats. Examples of informal communication include email, phone calls, conversations in the hallway, and impromptu meetings12. The sponsor is using informal communication to communicate with the team, as these methods are convenient, flexible, and personal. However, informal communication may also have some drawbacks, such as lack of documentation, inconsistency, and potential for misunderstanding3. Therefore, the sponsor should also use formal communication when necessary, such as for official reports, contracts, and presentations4.
Question 167
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
Explanation:
A maintenance window is a predefined period of time during which planned changes or updates can be performed on a system or network with minimal impact on the users or business operations1. A project manager should consider the maintenance window next when deploying a new networking device into an existing production environment, as it will help to reduce the risk of downtime, disruption, or errors. A maintenance window should be scheduled in advance, communicated to the stakeholders, and aligned with the change management plan2.
Question 168
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
Explanation:
According to Four agile ceremonies, demystified, one of the Scrum ceremonies is the daily stand-up, which is a short meeting to discuss progress and identify blockers. Blockers are any issues or impediments that prevent the team from completing their tasks or achieving their goals. Reviewing project blockers during the daily stand-up helps the team to resolve them quickly, collaborate effectively, and stay on track1. The other options are not likely to take place during a Scrum ceremony, as they are either part of the initial project planning or outside the scope of Scrum.
Question 169
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
Explanation:
Removing access means revoking the contractor's permissions to access the project data, systems, and devices after the project is closed. This is a crucial security measure to prevent unauthorized access, misuse, or theft of sensitive data by external parties. Closing contracts, project sign-off, and project evaluation are important steps in the project closure process, but they do not necessarily prevent data theft by themselves. They may involve formal agreements, documentation, and feedback, but they do not address the technical aspects of data security. Reference = CompTIA Project+ Study Guide: Exam PK0-005, Third Edition, Chapter 14: Closing the Project, page 3771; 9 Ways to Prevent Third-Party Data Breaches in 20232; 3 Ways to Prevent Data Theft by Contractors3
Question 170
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
Explanation:
The execution phase is when the project manager and the team execute the project plan, deliver the project outputs, and monitor and control the project performance. This includes tracking and managing the project budget, scope, schedule, quality, and risks. Making adjustments to the budget based on the actual project expenditures is part of the monitoring and controlling process in the execution phase. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, p. 263.