PMI PgMP Practice Test - Questions Answers, Page 38

List of questions
Question 371

What would prevent a program manager from completing program closure once a program has been completed?
Question 372

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized.
After further analysis of the performance indicators, the program manager should do which of the following?
Question 373

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.
To ensure the realization of long-term benefits, what should the program manager use?
Question 374

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?
Question 375

During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.
What should the program manager do to address the situation?
Question 376

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.
In what phase is the risk management plan created?
Question 377

A design and production company's program comprises the design and manufacture of complex parts. During the yearly strategy alignment meeting, the program manager notices that a peer program manager started a project to develop a new manufacturing technology to further reduce operations costs.
What should the program manager do to incorporate this new technology into the program?
Question 378

The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.
What should the program manager do next?
Question 379

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.
What should the program manager do to monitor and control the supplier?
Question 380

During a program's definition phase, it is determined that the best approach for delivering the program's intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers.
The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
Question