ExamGecko
Home Home / PMI / PgMP

PMI PgMP Practice Test - Questions Answers, Page 38

Question list
Search
Search

List of questions

Search

Related questions











What would prevent a program manager from completing program closure once a program has been completed?

A.
Failure to update the financial management plan
A.
Failure to update the financial management plan
Answers
B.
Failure to update the benefits register
B.
Failure to update the benefits register
Answers
C.
Incomplete realization of all program benefits
C.
Incomplete realization of all program benefits
Answers
D.
Failure to obtain program steering committee approval
D.
Failure to obtain program steering committee approval
Answers
Suggested answer: B

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized.

After further analysis of the performance indicators, the program manager should do which of the following?

A.
Extend the schedule to reduce costs and resource utilization.
A.
Extend the schedule to reduce costs and resource utilization.
Answers
B.
Expand the scope and continue the program until return-on-investment objectives can be met.
B.
Expand the scope and continue the program until return-on-investment objectives can be met.
Answers
C.
Recommend cancellation of the program based on performance metrics.
C.
Recommend cancellation of the program based on performance metrics.
Answers
D.
Transition the existing program results to the appropriate operational area.
D.
Transition the existing program results to the appropriate operational area.
Answers
Suggested answer: C

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.

To ensure the realization of long-term benefits, what should the program manager use?

A.
Benefits register
A.
Benefits register
Answers
B.
Benefits sustainment plan
B.
Benefits sustainment plan
Answers
C.
Benefits management plan
C.
Benefits management plan
Answers
D.
Benefits transition plan
D.
Benefits transition plan
Answers
Suggested answer: A

Explanation:

Reference: https://uwaterloo.ca/ist-project-management-office/methodologies/program-management/program-benefit-delivery/benefits-register

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.

Which will provide the greatest value to clarify stakeholder perceptions?

A.
Performing a stakeholder analysis
A.
Performing a stakeholder analysis
Answers
B.
Updating the stakeholder communications requirements
B.
Updating the stakeholder communications requirements
Answers
C.
Redistributing the benefits management plan
C.
Redistributing the benefits management plan
Answers
D.
Redistributing the program charter
D.
Redistributing the program charter
Answers
Suggested answer: B

During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.

What should the program manager do to address the situation?

A.
Review and update the detailed stakeholder list.
A.
Review and update the detailed stakeholder list.
Answers
B.
Review and update the stakeholder engagement plan.
B.
Review and update the stakeholder engagement plan.
Answers
C.
Execute the component project's communications management plan.
C.
Execute the component project's communications management plan.
Answers
D.
Update the risk register.
D.
Update the risk register.
Answers
Suggested answer: C

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.

In what phase is the risk management plan created?

A.
Program definition
A.
Program definition
Answers
B.
Program execution management
B.
Program execution management
Answers
C.
Program delivery
C.
Program delivery
Answers
D.
Program risk management planning
D.
Program risk management planning
Answers
Suggested answer: D

Explanation:

Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-16-risk-management-planning-project-management/

A design and production company's program comprises the design and manufacture of complex parts. During the yearly strategy alignment meeting, the program manager notices that a peer program manager started a project to develop a new manufacturing technology to further reduce operations costs.

What should the program manager do to incorporate this new technology into the program?

A.
Work with the project managers to update the program's risk register by evaluating this new technology's ROI.
A.
Work with the project managers to update the program's risk register by evaluating this new technology's ROI.
Answers
B.
Incorporate the new benefit to be obtained from this technology into the program's transition plan.
B.
Incorporate the new benefit to be obtained from this technology into the program's transition plan.
Answers
C.
Analyze the benefits management plan to determine any new risks this new technology may introduce.
C.
Analyze the benefits management plan to determine any new risks this new technology may introduce.
Answers
D.
Update the benefits management plan with an analysis of the new technology's potential benefits.
D.
Update the benefits management plan with an analysis of the new technology's potential benefits.
Answers
Suggested answer: C

The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.

What should the program manager do next?

A.
Update the program benefits management plan and risk register.
A.
Update the program benefits management plan and risk register.
Answers
B.
Implement the mitigation plan for the identified risk.
B.
Implement the mitigation plan for the identified risk.
Answers
C.
Adjust the program scope to avoid the risk.
C.
Adjust the program scope to avoid the risk.
Answers
D.
Document the risk and create a mitigation plan.
D.
Document the risk and create a mitigation plan.
Answers
Suggested answer: D

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.

What should the program manager do to monitor and control the supplier?

A.
Use expert judgment, and update the program procurement plan.
A.
Use expert judgment, and update the program procurement plan.
Answers
B.
Seek stakeholder approval of program procurement management activities.
B.
Seek stakeholder approval of program procurement management activities.
Answers
C.
Examine performance reports, audits, and inspections.
C.
Examine performance reports, audits, and inspections.
Answers
D.
Review proposal evaluation criteria, risk analyses, and mitigation strategies.
D.
Review proposal evaluation criteria, risk analyses, and mitigation strategies.
Answers
Suggested answer: D

During a program's definition phase, it is determined that the best approach for delivering the program's intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers.

The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?

A.
Make-or-buy decisions, alternatives analyses, approach to competition, and best mix of contract types
A.
Make-or-buy decisions, alternatives analyses, approach to competition, and best mix of contract types
Answers
B.
Requests for proposals (RFPs), proposal evaluation criteria, contract management, and best mix of contract types
B.
Requests for proposals (RFPs), proposal evaluation criteria, contract management, and best mix of contract types
Answers
C.
RFPs, alternatives analyses, approach to competition, and requests for quotes (RFQs)
C.
RFPs, alternatives analyses, approach to competition, and requests for quotes (RFQs)
Answers
D.
Make-or-buy decisions, proposal evaluation criteria, contract management, and RFQs
D.
Make-or-buy decisions, proposal evaluation criteria, contract management, and RFQs
Answers
Suggested answer: D
Total 451 questions
Go to page: of 46