Question 201

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
Question 202

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?
Question 203

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
Question 204

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
Question 205

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?
Question 206

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
Question 207

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?
Question 208

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
Question 209

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
Question 210

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?
Question