Question 191

Report
Export
Collapse

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Flat
Flat
Projectized
Projectized
Weak matrix
Weak matrix
Functional
Functional
Suggested answer: C

Explanation:

A weak matrix organizational structure is one where the project manager has low authority and the functional manager has high authority. The project manager is considered to be a coordinator or an escalator, and the team members are primarily loyal to their functional units. This can cause issues with team motivation, communication, and performance1

asked 02/10/2024
Cynthia Gutknecht
46 questions

Question 192

Report
Export
Collapse

Which of the following best represents the project impact to a company's brand value?

The project is compliant with local and state laws and becomes the standard for new projects.
The project is compliant with local and state laws and becomes the standard for new projects.
The project promotes new initiatives to expand its benefit to other communities.
The project promotes new initiatives to expand its benefit to other communities.
The project exceeds the sales quota for the third quarter and raises the bar for next periods. The project meets the expected milestones and finishes on time and within budget.
The project exceeds the sales quota for the third quarter and raises the bar for next periods. The project meets the expected milestones and finishes on time and within budget.
Suggested answer: B

Explanation:

the brand of a project should deliver the message about its value and goals, and a proper brand helps the project get the necessary support and increases loyalty. The project that promotes new initiatives to expand its benefit to other communities is the one that best represents the project impact to a company's brand value, as it shows the company's vision, cause, and reputation.

asked 02/10/2024
John Russell
23 questions

Question 193

Report
Export
Collapse

Which of the following are primary features provided by a standard laaS solution? (Select two).

Encryption
Encryption
Storage
Storage
Networking
Networking
User interface
User interface
Access
Access
Database
Database
Suggested answer: B, C

Explanation:

According to What is Logging as a Service (LaaS)? - LogicMonitor, LaaS is a cloud-based log management platform that simplifies the management of infrastructure and application logs. LaaS offers a central location where you can store, analyze and visualize the content of all your logs. It works by ingesting logs from different sources, such as web servers, IoT devices, database servers and more. It then provides actionable output by organizing and restructuring the information within these logs. Therefore, storage and networking are primary features provided by a standard LaaS solution, as they enable the collection and transmission of logs from various sources to a centralized platform. Encryption, user interface, access, and database are not primary features of LaaS, as they are either optional or secondary aspects of the service.

asked 02/10/2024
Tillmon, Quinton
37 questions

Question 194

Report
Export
Collapse

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

Rollback plan
Rollback plan
Release plan
Release plan
Deployment plan
Deployment plan
Contingency plan
Contingency plan
Suggested answer: A

Explanation:

A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts1. A rollback plan is different from a contingency plan, which is a plan to deal with a specific risk event that may or may not occur2. A release plan and a deployment plan are not relevant to the scenario, as they are used to plan and execute the delivery and installation of the system, not to undo them. Therefore, the correct answer is A. Rollback plan.

asked 02/10/2024
Premier Lane
36 questions

Question 195

Report
Export
Collapse

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

CompTIA PK0-005 image Question 195 97085 10022024175307000000

CompTIA PK0-005 image Question 195 97085 10022024175307000000

Which of the following most likely represents the number of items in the backlog?

23
23
5
5
10
10
15
15
Suggested answer: A

Explanation:

The number of items in the backlog can be determined by looking at the ''Commitment'' column for each sprint in the provided chart. For Sprint 5, there is a commitment of completing 23 items, which is the highest among all sprints. This indicates that there are at least 23 items in the backlog to be worked on. This is consistent with the concept of agile project management, which allows for changes and additions to the project scope based on customer feedback and changing requirements.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Agile Project Management, page 321.CompTIA Project+ Cert Guide: Exam PK0-004, Chapter 9: Agile Project Management, page 287



asked 02/10/2024
Ahmad Khader
24 questions

Question 196

Report
Export
Collapse

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Agile works through larger integrated teams.
Agile works through larger integrated teams.
Agile promotes project manager ownership over deliverables.
Agile promotes project manager ownership over deliverables.
Agile reinforces the importance of comprehensive documentation.
Agile reinforces the importance of comprehensive documentation.
Agile has more customer involvement throughout development.
Agile has more customer involvement throughout development.
Agile is more flexible to allow for changes in scope.
Agile is more flexible to allow for changes in scope.
Agile is comprised of well-defined phases.
Agile is comprised of well-defined phases.
Suggested answer: D, E

Explanation:

Agile is a project management methodology that emphasizes customer collaboration, feedback, and adaptation throughout the project life cycle. Agile teams work in short iterations, called sprints, and deliver working increments of the product or service to the customer for review and approval. Agile teams can also respond to changing requirements and priorities by adjusting the scope, schedule, or quality of the project12. Waterfall, on the other hand, is a project management methodology that follows a linear and sequential process, where each phase of the project must be completed before moving on to the next one. Waterfall teams work with a fixed scope, schedule, and quality, and deliver the final product or service to the customer at the end of the project. Waterfall teams have less customer involvement and flexibility during the project development34.

asked 02/10/2024
luis lozano
35 questions

Question 197

Report
Export
Collapse

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

Encryption
Encryption
Multifactor authentication
Multifactor authentication
Quality assurance
Quality assurance
Password protection
Password protection
Suggested answer: A

Explanation:

Encryption is the process of transforming data into an unreadable format that can only be accessed by authorized parties who have the decryption key. Encryption is the best approach for the project manager to keep the PII confidential, as it protects the data from unauthorized access during storage and transmission12.

asked 02/10/2024
Mir Ali
42 questions

Question 198

Report
Export
Collapse

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Ticketing system
Ticketing system
Videoconference
Videoconference
Simple messaging system
Simple messaging system
Corporate social media
Corporate social media
Suggested answer: A

Explanation:

A ticketing system is a tool that allows the project manager to assign, track, and manage tasks for the testing phase. A ticketing system can help the resources to remain at their desks and only react when needed, because they can receive notifications, updates, and feedback on their tickets through email or other channels. A ticketing system can also help the project manager to monitor the progress, quality, and issues of the testing phase, and to generate reports and metrics. A ticketing system is different from a videoconference, which is a tool that allows the project team to communicate and collaborate in real time through audio and video. A videoconference is not suitable for allowing the resources to remain at their desks and only react when needed, because it requires their active participation and attention. A ticketing system is also different from a simple messaging system, which is a tool that allows the project team to exchange text messages and files. A simple messaging system is not effective for assigning, tracking, and managing tasks for the testing phase, because it lacks the features and functions of a ticketing system, such as prioritization, categorization, status, and history. A ticketing system is also different from a corporate social media, which is a tool that allows the project team to share information and ideas through online platforms. A corporate social media is not appropriate for allowing the resources to remain at their desks and only react when needed, because it may not be secure, reliable, or professional for the testing phase. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Project Execution1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 10: Project Execution2; The 15 best collaboration tools for productive teams3

asked 02/10/2024
Leandra Felipe
38 questions

Question 199

Report
Export
Collapse

Which of the following activities are important parts of the closing phase? (Select two).

Releasing resources
Releasing resources
Locking risks
Locking risks
Updating stakeholder register
Updating stakeholder register
Closing contracts
Closing contracts
Completing the work breakdown structure
Completing the work breakdown structure
Negotiating the next project
Negotiating the next project
Suggested answer: A, B

Explanation:

These are two of the key activities in the closing phase, as they involve finalizing the use of resources and resolving any remaining risks that may affect the project performance or quality.Reference= CompTIA Project+ Study Guide1, Chapter 12: Closing Phase Activities

asked 02/10/2024
Vipul Mehra
34 questions

Question 200

Report
Export
Collapse

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Development
Development
Production
Production
Testing
Testing
QA
QA
Suggested answer: B

Explanation:

This is where an existing application that is highly utilized by clients is moving to a new release, as it involves deploying and operating it in a live environment.Reference= CompTIA Project+ Study Guide1, Chapter 4: Project Environments

asked 02/10/2024
Mario Alba Barrero
30 questions
Total 299 questions
Go to page: of 30
Search

Related questions