A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, slating that there is a lack of information sharing among the team.

What should the project manager do?

A.

Delegate authority to the team members and ask them to submit weekly status reports instead.

Answers
A.

Delegate authority to the team members and ask them to submit weekly status reports instead.

B.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

Answers
B.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

C.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

Answers
C.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Answers
D.

Ask senior management for permission to hold in-person team meetings once each week.

Suggested answer: C