Question 1213 - PMP discussion
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.
Which action should the project manager take?
A.
Assign a dedicated resource to work on the documentation during the project.
B.
Create a specific sprint to deliver the project documentation.
C.
Focus on the documentation after the features are delivered.
D.
Make documentation a standard part of the definition of done (DoD).
Your answer: