Question 1212 - PMP discussion
A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the transformation manager arises.
What should the project manager do to manage this?
A.
Lead the parties to find a compromise.
B.
Analyze the context of the issue.
C.
Escalate the problem to the project sponsor.
D.
Evaluate the influence of the parties involved.