A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

A.

Consult with the project team members to gain their opinions.

Answers
A.

Consult with the project team members to gain their opinions.

B.

Ask the project team to delay the kick-off while resolving the concern.

Answers
B.

Ask the project team to delay the kick-off while resolving the concern.

C.

Meet with the project sponsor to obtain more information.

Answers
C.

Meet with the project sponsor to obtain more information.

D.

Request a copy of the project assumptions log for more insight.

Answers
D.

Request a copy of the project assumptions log for more insight.

Suggested answer: C