A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

A.

Escalate to the project management office (PMO) and request a solution for the requirements.

Answers
A.

Escalate to the project management office (PMO) and request a solution for the requirements.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

Answers
B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Answers
C.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

D.

Prioritize other items for the team and deal with the conflicting requirements later.

Answers
D.

Prioritize other items for the team and deal with the conflicting requirements later.

Suggested answer: C