Question 1229 - PMP discussion

Report
Export

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

A.

Requested an experienced resource as a replacement

Answers
A.

Requested an experienced resource as a replacement

B.

Negotiated additional time to complete the project

Answers
B.

Negotiated additional time to complete the project

C.

Allocated additional time for mentoring

Answers
C.

Allocated additional time for mentoring

D.

Convinced the critical resource to remain on the project

Answers
D.

Convinced the critical resource to remain on the project

Suggested answer: A