After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

A.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

Answers
A.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

B.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

Answers
B.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

C.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

Answers
C.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

D.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

Answers
D.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

Suggested answer: A